Title: Request for approval of an agreement with Isani Consultants, L.P., in the amount of $871,006, for engineering services to provide design, bidding, and construction phase engineering services in support of Plum Creek Channel Improvements on HCFCD Unit C102-00-00. (Sims Bayou Watershed, Bond ID CI-029, Project ID C102-00-00-X001, Agreement No. 2023-06, Precinct 2, MWDBE Contracted Goal: 20%).
Attachments: 1. 032624 AGMT ISANI 2023-06 backup.pdf
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): C102-00-00-X001
Vendor/Entity Legal Name (if applicable): Isani Consultants, L.P.

MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an agreement with Isani Consultants, L.P., in the amount of $871,006, for engineering services to provide design, bidding, and construction phase engineering services in support of Plum Creek Channel Improvements on HCFCD Unit C102-00-00. (Sims Bayou Watershed, Bond ID CI-029, Project ID C102-00-00-X001, Agreement No. 2023-06, Precinct 2, MWDBE Contracted Goal: 20%).
end

Background and Discussion:
The objective of the project is to repair and/or replace channel cross sections within the project limits. The project limits include approximately 5,500 linear feet along Plum Creek from the Gulf Freeway Service Road to the South Loop East Service Road. This portion of Plum Creek is owned and maintained by the City of Houston. Since this is a maintenance project, there is no specific prioritization framework score or quartile under the 2022 Prioritization framework approved by the Commissioners Court.

Expected Impact:
The channel is in poor condition and has collapsed along most of its segments. Once constructed, this project will provide a repair or replacement solution for each of the channel cross sections. Flood Control District staff will manage an engineering consultant team to execute the design stages of this project.

Alternative Options:
An alternative option is to not continue with design and construction of the project. Flood risk and deteriorated channel condition will remain the same.