Legislation Details

File #: 24-1487    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 3/13/2024 In control: Commissioners Court
On agenda: 3/26/2024 Final action: 3/26/2024
Title: Request for approval of an agreement with Pape-Dawson Consulting Engineers, LLC, dba Pape Dawson Engineers, in the amount of $349,410, for engineering services to complete a feasibility study of the East Fork and West Fork San Jacinto River Watershed and the Clear Creek Watershed to identify potential flood impacts due to unmitigated flows coming into Harris County from upstream counties and to evaluate the impacts of the increased flows on erosion and sedimentation issues. (San Jacinto River Watershed and Clear Creek Watershed, Bond ID Z-04, Project ID Z100-00-00-P043, Agreement No. 2023-44, Countywide, MWDBE Contracted Goal: 19%).
Attachments: 1. 032624 AGMT PAPE DAWSON 2023-44 CW agmt.pdf
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): Z100-00-00-P043
Vendor/Entity Legal Name (if applicable): Pape-Dawson Consulting Engineers, LLC dba Pape Dawson Engineers

MWDBE Contracted Goal (if applicable): 19%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an agreement with Pape-Dawson Consulting Engineers, LLC, dba Pape Dawson Engineers, in the amount of $349,410, for engineering services to complete a feasibility study of the East Fork and West Fork San Jacinto River Watershed and the Clear Creek Watershed to identify potential flood impacts due to unmitigated flows coming into Harris County from upstream counties and to evaluate the impacts of the increased flows on erosion and sedimentation issues. (San Jacinto River Watershed and Clear Creek Watershed, Bond ID Z-04, Project ID Z100-00-00-P043, Agreement No. 2023-44, Countywide, MWDBE Contracted Goal: 19%).
end

Background and Discussion:
This feasibility study will investigate the East Fork and West Fork San Jacinto River Watersheds and the Clear Creek Watershed to identify potential flood impacts due to unmitigated flows coming into Harris County from upstream counties and to evaluate the impacts of the increased flows on erosion and sedimentation issues.

Expected Impact:
This feasibility study will provide valuable information regarding potential future flood risks as well as potential future erosion issues in Harris County watersheds resulting from the unmitigated flows from adjacent upstream Counties. The feasibility study will provide the Flood Control District and Harris County planners with data needed to help Harris County coordinate with adjacent Counties regardin...

Click here for full text