Department: Toll Road Authority
Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): Ally General Solutions, LLC dba AGS Engineering and Construction
MWDBE Contracted Goal (if applicable): 100%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a First Amendment with Ally General Solutions, LLC dba AGS Engineering and Construction to revise the Scope of Services, increase compensation and extend the period of performance for construction engineering and inspection services associated with the installation of toll equipment and various projects in the amount of $200,000.00 (Countywide). MWDBE Contracted Goal: 100%.
end
Background and Discussion:
On September 28, 2021, Commissioners Court approved an agreement with Ally General Solutions, LLC dba AGS Engineering and Construction to provide construction engineering and inspection services for installation of toll equipment under the Roadside Toll Collection System project. The agreement also provides for coordination and oversight of toll equipment design standards, assist with interfacing and coordinating with various toll system vendors, and provide field maintenance support and oversight on toll system and equipment.
This amendment increases agreement amount from $550,000 to $750,000 and increases period of performance from 600 days to 1,250 days.
Expected Impact:
Funding for this request will come from the Toll Road Authority CIP project Toll System upgrades, maintenance, and capital support.
Alternative Options:
No other recommended solution for this identified need.
Alignment with Goal(s):
_ Justice and Safety