Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Renewal
Project ID (if applicable): 210021
Vendor/Entity Legal Name (if applicable): Two Sons Environmental Services
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible
Request Summary (Agenda Caption):
title
Request for approval of a renewal option with Two Sons Environmental Services for new construction and maintenance of on-site sewage facilities at various locations and related items for Harris County for the period of April 1, 2024 - March 31, 2025, at a cost of $300,000, and for the County Clerk to execute any applicable bonds to be received (210021), Justification for 0% MWDBE Participation Goal: 0% - Non-Divisible.
end
Background and Discussion:
A countywide term contract was created to provide Harris County Engineering Department and the Precincts with services to include new construction of On-Site Sewage Facilities and monthly maintenance and operation of existing On-Site Sewage Facilities at various locations within Harris County.
Expected Impact:
Harris County Engineering Department and each Precinct have the option to utilize this contract so that the contractor can provide monthly maintenance to their On-Site Sewage Facilities to maintain compliance with the Texas Commission on Environmental Quality.
Alternative Options:
Harris County Engineering Department and Precincts will need to have specific Texas Commission on Environmental Quality certified personnel for the Precincts to maintain or install their own On-Site Sewage Facilities.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
X Public Health
_ Transportation
_ Flooding
X Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
3/14/2023
245
Contract ...