Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Termination
Project ID (if applicable): UPIN 211033961530014
Vendor/Entity Legal Name (if applicable): Gunda Corporation, LLC
MWDBE Contracted Goal (if applicable):0
MWDBE Current Participation (if applicable):NA
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Request Summary (Agenda Caption):
title
Request for approval of a Mutual Termination Agreement with Gunda Corporation, LLC for improvements to the Westgreen Boulevard Segment 1 - from Morton Road to Clay Road Project, Precinct 4 (Previously Precinct 3), UPIN 211033961530014, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
The professional Services contract was originally executed on 12/14/2021 with Gunda Corporation, LLC and no amendment was made to the contract. This project has been mutually agreed upon for termination. UPIN 211033961530014, Precinct 4
Expected Impact: Termination of the agreement and return of the remaining funds.
Alternative Options: No alternative option. Both parties agree to mutually terminate the agreement.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
12/14/2021
30.
Recommendation that the County Judge execute amendments/agreements with:
Gunda Corporation, LLC, in the amount of $659,905.60 for engineering services for improvements to Westgreen Boulevard Segment 1 - from Morton Road to Clay Road in Precinct 4 (UPIN 211033961530014).
Location:
Address (if applicable):
Precinct(s): Precinct 4
Fiscal and Personnel Summ...
Click here for full text