Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 19104MF12P01
Vendor/Entity Legal Name (if applicable): Memorial Hills Utility District
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval of an interlocal agreement with Memorial Hills Utility District for project funding share of the total Project cost in connection with Memorial Hills Subdivision Drainage Improvements - 2018 project, UPIN 19104MF12P01, Precinct 1.
end
Background and Discussion:
The project is located in north Harris County in the Cypress Creek watershed, north of FM 1960, south of Cypress Creek, and east of Hardy Toll Road. The project area consists of approximately 84 acres of single-family residential homes. The existing system is a concrete curb and gutter and primarily drains into Briar Creek (K117-00-00). A 72" RCP with associated inlets also aids in draining the western portion of the site. The scope of the project includes constructing a drainage swale and underlying storm sewer behind the commercial tract along FM 1960.
The Memorial Hills Utility District benefits from the drainage improvements of the project and agreed to provide 50% of the total Project cost necessary for the construction of the Project. The Harris County agreed to provide 50% of the total Project cost necessary for the engineering, construction, and Right-of-Way acquisition for the Project.
Expected Impact:
This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. The interlocal agreement between Harris County and
Memorial Hills Utility Dist...