Legislation Details

File #: 24-0573    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/22/2024 In control: Commissioners Court
On agenda: 1/30/2024 Final action: 1/30/2024
Title: Request for approval of a change in contract with D & W Contractors, Inc in connection with Fountainview Sec 1 & 2 Subdivision Drainage Improvements - 2018, with an addition in the amount of $246,078.00, Job No. 22/0415-1, UPIN 19101MF12F01, Precinct 1, MWDBE Contracted Goal: 28%, MWDBE Current Participation: 54.6%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19101MF12F01
Vendor/Entity Legal Name (if applicable): D & W Contractors, Inc.


MWDBE Contracted Goal (if applicable): 28%
MWDBE Current Participation (if applicable): 54.6%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with D & W Contractors, Inc in connection with Fountainview Sec 1 & 2 Subdivision Drainage Improvements - 2018, with an addition in the amount of $246,078.00, Job No. 22/0415-1, UPIN 19101MF12F01, Precinct 1, MWDBE Contracted Goal: 28%, MWDBE Current Participation: 54.6%.
end

Background and Discussion:
The Fountain view Subdivision is in the Aldine area of northern Harris County, Precinct 1 and includes the following streets: Farley Drive, Picton Drive, McCracken Rd, Indianola Drive, Mendota Lane, Surles Drive and Vickita Drive. The subdivision is about a half mile northwest of the intersection of US 59 Eastex Freeway and Aldine-Bender Road. The subdivision is surrounded by tributaries of Greens Bayou, including P133-0000 to the north, P133-04-00 to the west, and P133-03-00 to the east. The proposed drainage improvements include upsizing 1,730 feet of storm sewer system with diameters ranging from 24" to 48", capacity improvements to 3,660 feet of the P133-03-00 and P133-04-00 grass lined ditches, the addition of a 12 acre-feet detention pond to the north of the subdivision, the installation of 1,400 feet of buried storm sewer system in P133-03-00 with sizes ranging from 36" RCP to 7'x4' RCB, and in-kind replacement of roadway, curb, and gutter sections that are disturbed.

The Change in contract request includes new items for the following:
* PCO - 3 - Additional line item needed for th...

Click here for full text