Legislation Details

File #: 24-0560    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 1/22/2024 In control: Commissioners Court
On agenda: 1/30/2024 Final action: 1/30/2024
Title: Request for approval of an award on the basis of low bid to Main Lane Industries, Ltd. in the amount of $2,409,965 for drainage improvements of the Halls Bayou Tributary P118-14-00 for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (230412), MWDBE Contracted Goal: 24%.
Attachments: 1. 24-0560 Award - Main Lane Industries, Ltd. Job No. 230412
Department: Purchasing
Department Head/Elected Official: DeWight Dopslauf

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 230412
Vendor/Entity Legal Name (if applicable): Main Lane Industries, Ltd.

MWDBE Contracted Goal (if applicable): 24%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to Main Lane Industries, Ltd. in the amount of $2,409,965 for drainage improvements of the Halls Bayou Tributary P118-14-00 for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received (230412), MWDBE Contracted Goal: 24%.
end

Background and Discussion:
The P518-10-00-E001 (Phase 2) project is in northeast Houston in Harris County Precinct 2. The purpose of the project is to implement channel conveyance improvements (desilt, slope stabilization, crossing replacements, culvert repair) along P118-14-00 between the Hopper and Little York stormwater detention basins installed during the P518-10-00-E002 (Phase 1) project. Phase 2 will be constructed using remaining CDBG-DR 2017 Hurricane Harvey Round 1 grant funds remaining from Phase 1.

Expected Impact:
This project seeks to reduce flood risks and strengthen resiliency in Harris County by alleviating property and structural damages to the adjacent community. The objective is to restore channel capacity and increase conveyance of storm water along P118-14-00. This will reduce the financial, physical, and emotional burden flood damages place on homeowners. It will also reduce the financial impact of recovery costs to Harris County and federal flood insurance program.

Alternative Options:
There are no viable alternatives to this item being requested. Should this project not be approved to advertise for bids, existing conditions would not be imp...

Click here for full text