Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Financial Authorization
Project ID: 22103MF2E801
Vendor/Entity Legal Name (if applicable): Any applicable landowner and/or property interest holder
MWDBE Contracted Goal (if applicable): Not Applicable
MWDBE Current Participation (if applicable): Not Applicable
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to purchase a certain tract for a negotiated price for Harris County for the public project known as Harris County Precinct Three for LMI Sidewalks and Trail Project (Phase 2), tract number 5A, for $763.00 which is $394.00 over the appraised value, UPIN 22103MF2E801, Precinct 3.
end
Background and Discussion:
Design and construction of 5' concrete sidewalk.
Expected Impact:
Improved safety as visibility is increased for right turns at intersections and improved driveway slope to meet Harris County standards.
Alternative Options:
Due to the minimal impacts anticipated, there were no alternatives considered.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
1/10/2023
77
Public necessity
Location:
Address (if applicable): 11202 Huffmeister, Cypress, TX 77065
Precinct(s): Precinct 3
Fiscal and Personnel Summary
Service Name
FY 24
FY 25
Next 3 FYs
Incremental Expenditures (do NOT write values in thousands or millions)
Labor Expenditures
$
$
$
Non-Labor Expenditures
$763.00
$
$
Total Incremental Expenditures
$763.00
$
$
Funding Sources (do NOT write values in thousands or millions)
Administrative Approval Only - Funding Sources approval will be submitted at later date.
1070 - Mobility Fund
...