Request Summary (Agenda Caption):
title
Request for approval to negotiate with Consor Engineers LLC for Professional Engineering Services for the design of Bridge Repair - Stuebner Airline Rd Bridge K100 - 2024, UPIN 24103MF3A801, Precinct 3.
end
Background and Discussion:
The request is to engage Consor Engineers LLC to conduct site investigation and design recommended repairs to ensure longevity of the bridge.
Expected Impact:
The project will address current bridge repairs needed to ensure mobility for the community.
Alternative Options:
If not action is taken, the bridge will continue to experience deterioration that would need larger scale repairs in the future.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
Location:
Address (if applicable):
Precinct(s): Precinct 3
Fiscal and Personnel Summary
Service Name
Road Construction
FY 24
FY 25
Next 3 FYs
Incremental Expenditures (do NOT write values in thousands or millions)
Labor Expenditures
$
$
$
Non-Labor Expenditures
$
$
$
Total Incremental Expenditures
$
$
$
Funding Sources (do NOT write values in thousands or millions)
Existing Budget
Other
$.
$
$
Choose an item.
$
$
$
Choose an item.
$
$
$
Total Current Budget
$ .
$
$
Additional Budget Requested
Choose an item.
$
$
$
Choose an item.
$
$
$
Choose an item.
$
$
$
Total Additional Budget Requ...
Click here for full text